APT pressure test carried out at 7bar on a 760mm steel the test was completed in 42hours this was a saving 57hours.


Contact us for information on our other services including the APT testing for pipework up to 7bar and lengths up to 11km as this system can reduce the testing times as calculated in the MSL1 documents this means you can get critical supplies up and running faster. #testing #mtscontracting #apt


 
 
 